Short answer
User acceptance testing (UAT) is the moment when the client or future users check whether the system fits their work and decide on acceptance. For it to go smoothly, prepare five things before you start: acceptance criteria agreed with the client, 10-30 scenarios in business language, an environment with realistic data, a schedule with time for fixes and a sign-off record. UAT comes after QA testing, not instead of it. It usually takes 1-2 weeks per release or stage.
UAT vs QA testing
| QA testing | user acceptance testing (UAT) | |
|---|---|---|
| who tests | the QA team | the client, future users |
| question | does the system work according to the specification | does the system fit our work |
| scope | including edge cases and errors | typical everyday tasks |
| scenario language | technical, with test data | business, e.g. “issue a corrective invoice” |
| result | a list of defects, a test report | an acceptance decision and a sign-off record |
If the client finds defects like “the button doesn’t work” in UAT, QA testing was too short. UAT should rather reveal gaps in how the requirements were understood.
Step 1: acceptance criteria
Every feature to be accepted needs criteria the client can check. The “Given… when… then…” format works well:
Given an invoice issued last month, when I issue a correction for some of its items, then the system creates a corrective invoice with the correct VAT difference and sends it to the customer.
You agree the criteria before the feature is built, not before UAT. Then UAT checks what both sides agreed to.
Step 2: scenarios in business language
- 10-30 scenarios per release, one per important user task;
- written so that someone who didn’t build the system can run them;
- with data the client knows, e.g. their real products or typical amounts;
- each scenario has a “result: pass / fail” field and room for a comment.
Example scenario:
| step | action | expected result |
|---|---|---|
| 1 | log in as the accountant | you see the list of invoices for the current month |
| 2 | open an October invoice and choose “correction” | a correction form with the invoice items |
| 3 | change the quantity in one item and save | a new corrective invoice with the VAT difference |
| 4 | check the test customer’s inbox | an email with the correction as a PDF |
Step 3: environment and data
- a separate UAT environment, or staging frozen for the duration of the tests;
- accounts for every role the client tests;
- data similar to real data, but not personal data from production, unless there is a legal basis and consent;
- real payments and emails to real customers switched off.
Step 4: schedule
| stage | time |
|---|---|
| short training for testers on the client side | 1-2 hours |
| testing according to the scenarios | 3-5 working days |
| reviewing reports with the client, splitting them into defects and changes | 1 meeting |
| fixing blocking defects | as agreed, usually a few days |
| recheck and acceptance decision | 1-2 days |
The most common problem is lack of time on the client side. Book the people with a calendar in hand before you set the UAT date.
Step 5: sign-off record
The sign-off record closes UAT and contains:
- the system version and the scope of acceptance;
- the list of scenarios with results;
- open defects with severity and a fix date;
- the decision: accepted without reservations, accepted with reservations, or not accepted;
- signatures of the decision makers.
An email saying “looks OK” is not acceptance. In three months nobody will remember exactly what was accepted.
How I can help
As part of manual testing I prepare UAT scenarios together with the client, run the tests on the client side, collect reports and keep defects separate from changes. Before that I run full QA testing, so UAT doesn’t turn into a hunt for basic bugs. Describe your project and acceptance date in the contact form.