User acceptance testing (UAT): how to prepare it together with the client

How UAT differs from QA testing, how to prepare scenarios the client will actually go through, and how to close acceptance with a sign-off record, not an email.

author
Artur Machowski, Senior QA Engineer
published
reading
6 min

Short answer

User acceptance testing (UAT) is the moment when the client or future users check whether the system fits their work and decide on acceptance. For it to go smoothly, prepare five things before you start: acceptance criteria agreed with the client, 10-30 scenarios in business language, an environment with realistic data, a schedule with time for fixes and a sign-off record. UAT comes after QA testing, not instead of it. It usually takes 1-2 weeks per release or stage.

UAT vs QA testing

QA testinguser acceptance testing (UAT)
who teststhe QA teamthe client, future users
questiondoes the system work according to the specificationdoes the system fit our work
scopeincluding edge cases and errorstypical everyday tasks
scenario languagetechnical, with test databusiness, e.g. “issue a corrective invoice”
resulta list of defects, a test reportan acceptance decision and a sign-off record

If the client finds defects like “the button doesn’t work” in UAT, QA testing was too short. UAT should rather reveal gaps in how the requirements were understood.

Step 1: acceptance criteria

Every feature to be accepted needs criteria the client can check. The “Given… when… then…” format works well:

Given an invoice issued last month, when I issue a correction for some of its items, then the system creates a corrective invoice with the correct VAT difference and sends it to the customer.

You agree the criteria before the feature is built, not before UAT. Then UAT checks what both sides agreed to.

Step 2: scenarios in business language

  • 10-30 scenarios per release, one per important user task;
  • written so that someone who didn’t build the system can run them;
  • with data the client knows, e.g. their real products or typical amounts;
  • each scenario has a “result: pass / fail” field and room for a comment.

Example scenario:

stepactionexpected result
1log in as the accountantyou see the list of invoices for the current month
2open an October invoice and choose “correction”a correction form with the invoice items
3change the quantity in one item and savea new corrective invoice with the VAT difference
4check the test customer’s inboxan email with the correction as a PDF

Step 3: environment and data

  • a separate UAT environment, or staging frozen for the duration of the tests;
  • accounts for every role the client tests;
  • data similar to real data, but not personal data from production, unless there is a legal basis and consent;
  • real payments and emails to real customers switched off.

Step 4: schedule

stagetime
short training for testers on the client side1-2 hours
testing according to the scenarios3-5 working days
reviewing reports with the client, splitting them into defects and changes1 meeting
fixing blocking defectsas agreed, usually a few days
recheck and acceptance decision1-2 days

The most common problem is lack of time on the client side. Book the people with a calendar in hand before you set the UAT date.

Step 5: sign-off record

The sign-off record closes UAT and contains:

  • the system version and the scope of acceptance;
  • the list of scenarios with results;
  • open defects with severity and a fix date;
  • the decision: accepted without reservations, accepted with reservations, or not accepted;
  • signatures of the decision makers.

An email saying “looks OK” is not acceptance. In three months nobody will remember exactly what was accepted.

How I can help

As part of manual testing I prepare UAT scenarios together with the client, run the tests on the client side, collect reports and keep defects separate from changes. Before that I run full QA testing, so UAT doesn’t turn into a hunt for basic bugs. Describe your project and acceptance date in the contact form.

Frequently asked questions

What is user acceptance testing (UAT)?

Testing in which the client or future users check whether the system does what they need in their daily work. It ends with an acceptance decision. It doesn't replace QA testing, it comes after it.

Who prepares acceptance tests?

The scenarios are best prepared by a tester or analyst together with the client, based on the acceptance criteria. They are run by people on the client side who will use the system. The tester helps, collects reports and keeps the schedule.

How long does acceptance testing take?

Usually 1-2 weeks per release or project stage, plus time for fixes and a recheck. Less if full QA testing was done before UAT and the client only tests business scenarios.

How does acceptance testing differ from system testing?

System testing is done by the QA team and checks whether the system works according to the specification, including edge cases. UAT is done by the client and checks whether the system fits their work. A UAT defect often means a wrong requirement, not wrong code.

What if the client raises new requirements during UAT?

Separate defects from changes. A defect is something that doesn't meet an agreed acceptance criterion. A new requirement goes to the backlog and doesn't block acceptance, unless both sides agree otherwise.